Project Description

Plant Vogtle Units 3 & 4 | Cooling Tower Foundation & Hot Water Intake Tunnels

LOCATION: Waynesboro, GA
OWNER: Georgia Power Company

PROJECT SCOPE:

  • Excavate 250,000 cy 30’ depths for tunnel construction
  • Install 56- 6’ diameter caissons 120’depth
  • Form & pour 2- 20’ x 20’ box culverts 275’ long
  • Poured 9,600 cy of concrete
  • Utilized 1,100 tons of rebar
  • Installed concrete pile caps
  • 90,000 cy of structural backfill